Warehouse
Layout Design
RACK & LAYOUT, CAD DESIGN, +PROJECT MNGMT
- 285K SF || 32’ clear || VNA Racking || High Pile Storage
Sourced all vendors / contractors for all CapX expenses
Coordinated install dates & scheduled timelines across teams.
Determined product profiles & designed VNA racking layout.
Designed inbound, outbound, production, and the conveyor system.
Oversaw install of all racking, electrical, and mechanical needs.
Incorporated a "skeleton build" rack install saving $172K on steel.
Overall materials/service savings for the project were amounted to $452k
Highlights
$3M CAPX BUDGET MANAGEMENT
Sourced all vendors/contractors for all CapX expenses.
Incorporated a "skeleton build" rack install saving $172K on steel.
Overall materials/service savings for the project amounted to $452k
IFC DRAWING EVALUATION
Discovered $24k worth of savings in electrical plans in IFC drawing.
Discovered AMP load significantly under planned for production /packaging area.
Facilitated additional tour of D.C. with Contractors & Designers to ensure no other misses in plans.